"All
tunnel walls are now complete, the roof is on and 80% of the tunnel
excavation is complete with the interior fit out underway," said
Helen Cook, NZTA Communications Manager for Victoria Park Alliance.
"The birdcage is also on the move back to its original location
above the new section of completed tunnel and should be in place
before Easter."
The 450m, three-lane, one-way northbound tunnel is being constructed using a 'cut and cover' method utilised by Fletcher Construction previously on the New Lynn Rail Trench.
"We still have a steady supply of concrete being delivered to
various locations within the work zone with 6 to 10 different jobs
per day with multiple deliveries per job," says Trevor Van Egmond,
Operations Manager (Auckland) for Firth. 
Firth has supplied 9,900m3 of concrete to the project this year, keeping the team at the Hamer street plant extremely busy.