paving planner
measuring paving
online resources

Infrastructure - Victoria Park Tunnel

<  Back Tuesday, 7 September 2010

Firth unplugs the bottleneckVic Tunnel

Over the last 10 years the bottleneck between the Auckland Harbour Bridge and the Newmarket Viaduct has slowly become worse and worse. So it is with some relief that motorists are seeing the 450 metre-long Victoria Park Tunnel project get underway.

Firth Industries Ltd has been contracted as the concrete supplier on the new $340 million tunnel. The tunnel will take three northbound traffic lanes while the existing Victoria Park viaduct will be reconfigured to carry four southbound lanes.  Through St Marys Bay the motorway is being widened by one lane in each direction to 10 lanes plus a citybound bus-only lane.

"This is a substantial job for Firth and we are delighted to be supplying concrete for this important roading project for Auckland," says Gavin Allden Northern Regional Sales Manager for Firth Industries.

"We are very well placed geographically to supply to the project as our Hamer Street, Westhaven plant is the only Certified concrete plant in downtown Auckland, and is situated within walking distance of the site," he says. "The close proximity of our plant to the project site means we are easily able to meet the demands of the job at any time of the day and night without having to worry about travelling delays and adding to congestion, which is a huge plus." 

Firth has been supplying mixes since construction of the 'cut-and-cover' tunnel began in April. This construction method involves building the tunnel walls first, followed by installation roof beams, excavation of the tunnel trench and, finally, pouring the 800mm thick floor slabs. Firth is also the supplier to the Fletcher's pre-cast yard in Tauranga where the tunnel's 176 30-tonne roof beams are being made. The other 190 beams are being made by HEB Pre-Cast.

More than half of the 2000 concrete piles required for the tunnel walls and retaining walls on the tunnel approach and exit had been completed by the end of August.

The majority of the concrete work is expected to be completed by late 2011 with the new motorway opening in 2012. An event that will certainly be looked forward to by Auckland motorists.