Kereru Gorge Bridge Aerial Shot

Firth Hastings produce the goods for Kererū Gorge culvert project

Cyclone Gabrielle devastated many parts of the country in February 2023 with the Hawke’s Bay taking the brunt of this major weather event. Nineteen bridges and culverts in the region were damaged, including the Kererū Gorge culvert, which was washed out, completely wiping out the existing 1.5m culvert and making the road impassable.  

Kereru Gorge Bridge Aerial Shot

Reinstating this critical road was high on the list for the region by NZ Transport Agency Waka Kotahi and Hastings District Council, which determined it would need to be future proofed with a more robust culvert system designed to handle major events such as Gabrielle.

To view a video of the overall project, click here

Fulton Hogan for the Napier / Hastings District were handed the tricky job of installing a culvert in the gorge that was 10 x larger than the original at a whopping 15m wide, supported by Stantec, the engineers who designed the replacement system. Key to the project would be selecting the concrete supplier that was not only capable of delivering up to 300m3 of concrete in a 10 -12 hour period but who also had the technical know-how to deliver the solutions required for this demanding project. 

Firth Truck & Pump Kereru Gorge

“We actually put out a request to the various batch plant concrete providers within Hawke’s Bay and then we spoke with each of them putting forward a series of requirements,” says Michael Stiebel, Project Manager Civil (Structures) Fulton Hogan Napier. “The Firth Hastings team were chosen, and we are glad they were.”

Kereru Gorge Concrete

Firth’s technical expertise shines 

“Once we were chosen to be the provider for the Kererū gorge project we started designing the mixes that would be used for the various stages of the culvert project,” explains Tim Bulmer, Regional Materials Manager (Bay of Plenty) for Firth. “Initially, the plan was to use a 30MPa concrete with a fly ash addition for the main structure of the culvert to manage the huge heat normally generated on large pours.”

Various trials were undertaken at the Firth Mt Maunganui laboratory and the Hastings plant to achieve both the low density and low heat characteristics, Firth proposed using GGBS (slag).  

 “The laboratory trials with a 60% slag replacement yielded promising results, leading to another plant trial,” says Tim. “This time the temperature probes showed a much lower temperature and met the other performance criteria. We had come up with a design which was then signed off by Stantec.”

Kereru Gorge Site

After achieving the desired mix design the work began for Firth Hastings to get the GGBS from Tauranga to Hastings, a six-hour journey, and then to allow for the 90-minute trip for deliveries of concrete to the project site. 

“Despite all of these complexities we successfully supplied large quantities of concrete, including pours of approximately 280m³ the week before Christmas and then another 250m³ on 4 Jan this year,” says Lester Wagner, Area Operations / Sales Manager (Hawke's Bay) for Firth.

Kereru Gorge, Firth Truck

 “Especially in the early stages we were presenting the concrete’s stats to Stantec to show them that the targets were not just being met, but bettered,” adds Michael. “The initial requirement was not to exceed the 65 degree mark and to achieve 3MPa in the first 48 hours. From the early stages the concrete was hitting 10MPa. This gave everyone confidence that everything was going well.”

“Layering either side of the installation evenly is essential and of course we couldn’t work on the next layer until the previous layer had cooled enough. Firth and the concrete performed very well.” 

In review …

“Communication and coordination between ourselves and Firth, was absolutely essential and we got that from them and more,” adds Michael. “Sometimes it was difficult to get the volumes exactly right and after talking to the Firth team they were able to help us out. We all worked through issues together. The project was opened in time for the Easter holiday break this year with the official opening on 17 April."

“This was a complex and difficult project and having Firth working with us was exactly what was needed for its success. Would I recommend Firth?  Yes - absolutely.” 

 

Principal:                            Hastings District Council

Project:                              Kererū Gorge Culvert installation 

Designer:                           Stantec 

Main Contractor:             Fulton Hogan Napier 

Location:                           Kererū Gorge – 90 mins from Hastings

Product:                            Firth Engineered Concrete